TransCanada Canadian Mainline Notice 3374724881

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

Notice Type
Capacity Constraint

Effective Start Date Time
07/24/2026 5:44 pm

Subject
Emerson Extension Line 1 Pipeline System Maintenance

Notice Text

TC Energy provides notice that in-line inspections will be conducted on the Emerson Extension Line 1 Pipeline System from August 5th to 11th gas days inclusive.  

During this period, discretionary services to Emerson 1 may be impacted with capacity at the export point expected to be reduced to ~425 TJ/d. Firm services are not expected to be impacted. 

 

Please note that system capacities are variable due to many factors including forecast delivery distribution, ambient temperatures, gas stream energy content, facility availability, and interconnect assistance.  Actual capacities on the day may vary due to changes to the maintenance schedule, unplanned events, and differences between forecast and actual operating conditions. 

 

QUESTIONS  

If you have any questions or require further information, please contact your Marketing Representative. 



Notice Type
Capacity Constraint

Effective Start Date Time
07/24/2026 5:44 pm

Subject
Emerson Extension Line 1 Pipeline System Maintenance

Notice Text

TC Energy provides notice that in-line inspections will be conducted on the Emerson Extension Line 1 Pipeline System from August 5th to 11th gas days inclusive.  

During this period, discretionary services to Emerson 1 may be impacted with capacity at the export point expected to be reduced to ~425 TJ/d. Firm services are not expected to be impacted. 

 

Please note that system capacities are variable due to many factors including forecast delivery distribution, ambient temperatures, gas stream energy content, facility availability, and interconnect assistance.  Actual capacities on the day may vary due to changes to the maintenance schedule, unplanned events, and differences between forecast and actual operating conditions. 

 

QUESTIONS  

If you have any questions or require further information, please contact your Marketing Representative.