Tennessee Gas Pipeline Notice 400181

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  03/24/2026 7:01:13PM Notice End Date/Time:  03/25/2026 9:00:00am
Post Date/Time:  3/24/2026 7:01:13 PM Notice ID: 400181
Reqrd Rsp:  1 Rsp Date:  03/24/2026
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 03-25-2026 EC
Notice Text:

Effective Evening Cycle (9:00) for the gas day of Wednesday, March 25, 2026 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

NONE

 

METER RESTRICTIONS

·         ETP/TGP Wharton County Transport Ex Receipt Meter (Pin 411911) - through approx 10% of SA increases due to nominations in excess of operational capacity; 4,820 Dths

·         MATTEXPR/TGP Bernard Creek Receipt Receipt Meter (Pin 56009) - through approx 68% of IT increases due to nominations in excess of operational capacity; 16,750 Dths

·         TGP/SNG Bear Creek Injection Bienvi Delivery Meter (Pin 405367) - through 100% of SOP increases due to operational concerns; 30,000 Dths

·         HESS/TGP Ratcliffe: Dip 542B 101.1, Receipt Meter (Pin 421078) - through 100% of SIPss increases receipts due to displacement gas unavailable for backhaul; 10,000 Dths

SEGMENT RESTRICTIONS

·         STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 25,732 Dths

·         MLV 548 (Segment 542 BH) - through 100% of SA increases due to scheduled maintenance and nominations in excess of operational capacity; 5,000 Dths

·         STA 204 (Segment 204 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 4,200 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 367,132 Dths

·         MLV 314 East (Segment 314 BH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 269,720 Dths

·         STA 315 (Segment 315 BH) - through approx 83% of SOP increases due to nominations in excess of operational capacity; 323,085 Dths

·         STA 317 (Segment 317 BH) - through approx 89% of SOP increases due to nominations in excess of operational capacity; 58,807 Dths

·         STA 321 (Segment 321 FH) - through approx 67% of SOP increases due to nominations in excess of operational capacity; 320,904 Dths

·         STA 325 (Segment 324 FH) - through approx 27% of SOP increases due to nominations in excess of operational capacity; 76,225 Dths

·         MLV 330 (Segment 324 FH) - through approx 82% of SOP increases due to nominations in excess of operational capacity; 171,826 Dths

·         MLV 336 East (Segment 336 FH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 35,229 Dths

·         STA 224 (Segment 224 FH) - through approx 64% of SOP increases due to nominations in excess of operational capacity; 29,640 Dths

·         Z5hc North (Segment 299 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 275,428 Dths

·         STA 245 (Segment 245 FH) - through approx 98% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 468,613 Dths

·         STA 249 (Segment 249 FH) - through approx 97% of SOP increases due to nominations in excess of operational capacity; 321,410 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 224,608 Dths

LINEPACK RESTRICTIONS

Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.

 

STORAGE RESTRICTIONS

·         No Authorized Overrun Withdrawal Services under Rate Schedule FS-AO at the following storage fields:

o   Northern MA (460018)

o   Portland MA (460025)

o   Portland PA (460020)

o   Bear Creek PA (460017)

·         Customers who elected swing on storage or storage swing options for balancing (SOS or SSO) may only swing up to their  Maximum Daily Withdrawal (MDWQ) until further notice

·         No Authorized Overrun Withdrawal Services under Rate Schedule FS-F at the following storage field:

o   Pine Prairie Virtual (54628)

·         No Interruptible Storage Withdrawal Services under Rate Schedule IS at the following storage fields:

o   Northern MA (460018) IS-MA

o   Bear Creek PA (460017) IS-PA

·         No Loans or Park Withdrawals under Rate Schedule PAL utilizing the PAL-D or PAL-AO services system-wide

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  03/24/2026 7:01:13PM Notice End Date/Time:  03/25/2026 9:00:00am
Post Date/Time:  3/24/2026 7:01:13 PM Notice ID: 400181
Reqrd Rsp:  1 Rsp Date:  03/24/2026
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 03-25-2026 EC
Notice Text:

Effective Evening Cycle (9:00) for the gas day of Wednesday, March 25, 2026 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

NONE

 

METER RESTRICTIONS

·         ETP/TGP Wharton County Transport Ex Receipt Meter (Pin 411911) - through approx 10% of SA increases due to nominations in excess of operational capacity; 4,820 Dths

·         MATTEXPR/TGP Bernard Creek Receipt Receipt Meter (Pin 56009) - through approx 68% of IT increases due to nominations in excess of operational capacity; 16,750 Dths

·         TGP/SNG Bear Creek Injection Bienvi Delivery Meter (Pin 405367) - through 100% of SOP increases due to operational concerns; 30,000 Dths

·         HESS/TGP Ratcliffe: Dip 542B 101.1, Receipt Meter (Pin 421078) - through 100% of SIPss increases receipts due to displacement gas unavailable for backhaul; 10,000 Dths

SEGMENT RESTRICTIONS

·         STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 25,732 Dths

·         MLV 548 (Segment 542 BH) - through 100% of SA increases due to scheduled maintenance and nominations in excess of operational capacity; 5,000 Dths

·         STA 204 (Segment 204 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 4,200 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 367,132 Dths

·         MLV 314 East (Segment 314 BH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 269,720 Dths

·         STA 315 (Segment 315 BH) - through approx 83% of SOP increases due to nominations in excess of operational capacity; 323,085 Dths

·         STA 317 (Segment 317 BH) - through approx 89% of SOP increases due to nominations in excess of operational capacity; 58,807 Dths

·         STA 321 (Segment 321 FH) - through approx 67% of SOP increases due to nominations in excess of operational capacity; 320,904 Dths

·         STA 325 (Segment 324 FH) - through approx 27% of SOP increases due to nominations in excess of operational capacity; 76,225 Dths

·         MLV 330 (Segment 324 FH) - through approx 82% of SOP increases due to nominations in excess of operational capacity; 171,826 Dths

·         MLV 336 East (Segment 336 FH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 35,229 Dths

·         STA 224 (Segment 224 FH) - through approx 64% of SOP increases due to nominations in excess of operational capacity; 29,640 Dths

·         Z5hc North (Segment 299 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 275,428 Dths

·         STA 245 (Segment 245 FH) - through approx 98% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 468,613 Dths

·         STA 249 (Segment 249 FH) - through approx 97% of SOP increases due to nominations in excess of operational capacity; 321,410 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 224,608 Dths

LINEPACK RESTRICTIONS

Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.

 

STORAGE RESTRICTIONS

·         No Authorized Overrun Withdrawal Services under Rate Schedule FS-AO at the following storage fields:

o   Northern MA (460018)

o   Portland MA (460025)

o   Portland PA (460020)

o   Bear Creek PA (460017)

·         Customers who elected swing on storage or storage swing options for balancing (SOS or SSO) may only swing up to their  Maximum Daily Withdrawal (MDWQ) until further notice

·         No Authorized Overrun Withdrawal Services under Rate Schedule FS-F at the following storage field:

o   Pine Prairie Virtual (54628)

·         No Interruptible Storage Withdrawal Services under Rate Schedule IS at the following storage fields:

o   Northern MA (460018) IS-MA

o   Bear Creek PA (460017) IS-PA

·         No Loans or Park Withdrawals under Rate Schedule PAL utilizing the PAL-D or PAL-AO services system-wide

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.