NGTL Notice 3374724897

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

Notice Type
Capacity Constraint

Effective Start Date Time
08/05/2026 7:32 pm

Subject
NGTL Service (NEDA IT-D) - Otter Lake C/S

Notice Text

Due to unplanned maintenance at the Otter Lake Compressor station, the planned maintenance at the Meikle River C Compressor station will be deferred to a later date in efforts to prioritize FT service. Service allowable will remain at 0% IT-D and 100% FT-D for NEDA until further notice. At this time, return to service for the Otter Lake Compressor station is expected to be within 5-7 days.

 

For the purposes of the Daily Operating Plan (DOP) that will be published today:

  • A placeholder end date of August 12, 2026 will be used for the Otter Lake Compressor Station outage until more information is known
  • The Meikle River C Compressor Station outage will be removed and then be readded to the DOP at a later date once a new outage window has been determined


Notice Type
Capacity Constraint

Effective Start Date Time
08/05/2026 7:32 pm

Subject
NGTL Service (NEDA IT-D) - Otter Lake C/S

Notice Text

Due to unplanned maintenance at the Otter Lake Compressor station, the planned maintenance at the Meikle River C Compressor station will be deferred to a later date in efforts to prioritize FT service. Service allowable will remain at 0% IT-D and 100% FT-D for NEDA until further notice. At this time, return to service for the Otter Lake Compressor station is expected to be within 5-7 days.

 

For the purposes of the Daily Operating Plan (DOP) that will be published today:

  • A placeholder end date of August 12, 2026 will be used for the Otter Lake Compressor Station outage until more information is known
  • The Meikle River C Compressor Station outage will be removed and then be readded to the DOP at a later date once a new outage window has been determined