Guardian Pipeline Notice 1399

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP: 031752897

TSP Name: Guardian Pipeline, L.L.C.

Posting Date/Time: 04/01/2026 15:34:02

Notice Identifier: 131

Notice Stat Desc: Initiate

Notice Type Desc: Planned Service Outage

Notice Category: Critical

Subject: Planned Service Outage – Mainline Flow Northbound - Ridge Rd and Canal/Sunset Pipe Replacement

Notice Eff Date/Time: 05/19/2026 09:00:00

Notice End Date/Time: 05/24/2026 09:00:00

Critical Desc: Yes

Notice Scope: TSP SPECIFIC

Reqrd Rsp Desc: No

Response Date/Time:

Prior Notice Identifier:

Notice Text:
Due to planned maintenance, Guardian Pipeline, L.L.C, (GPL) mainline flow northbound will be unavailable for receipts and deliveries. GPL will reduce capacity at the following locations:

Joliet NBPL receipt capacity will be reduced 0 Dth.
Joliet MGT receipt and delivery will be reduced to 0 Dth.
Joliet Vector receipt and delivery will be reduced to 0 Dth.
Joliet Alliance receipt will be reduced to 0 Dth.
Joliet ANR receipt and delivery will be reduced to 0 Dth.
Joliet NGPL receipt will remain at 0 Dth.
Joliet Peoples receipt and delivery will be reduced to 0 Dth.
NNG Bluff Creek receipt will be available for the duration of the outage.

These capacity reductions begin Gas Day Tuesday, May 19, 2026, Timely Cycle and are anticipated to be in effect through Gas Day Saturday, May 23, 2026.

GPL does anticipate an impact to firm transportation services. Reservation rate credits will be applied pursuant to GPL's FERC Gas Tariff, General Terms and Conditions, Section 40.

Please contact your Commercial representative with any further questions.

TSP: 031752897

TSP Name: Guardian Pipeline, L.L.C.

Posting Date/Time: 04/01/2026 15:34:02

Notice Identifier: 131

Notice Stat Desc: Initiate

Notice Type Desc: Planned Service Outage

Notice Category: Critical

Subject: Planned Service Outage – Mainline Flow Northbound - Ridge Rd and Canal/Sunset Pipe Replacement

Notice Eff Date/Time: 05/19/2026 09:00:00

Notice End Date/Time: 05/24/2026 09:00:00

Critical Desc: Yes

Notice Scope: TSP SPECIFIC

Reqrd Rsp Desc: No

Response Date/Time:

Prior Notice Identifier:

Notice Text:
Due to planned maintenance, Guardian Pipeline, L.L.C, (GPL) mainline flow northbound will be unavailable for receipts and deliveries. GPL will reduce capacity at the following locations:

Joliet NBPL receipt capacity will be reduced 0 Dth.
Joliet MGT receipt and delivery will be reduced to 0 Dth.
Joliet Vector receipt and delivery will be reduced to 0 Dth.
Joliet Alliance receipt will be reduced to 0 Dth.
Joliet ANR receipt and delivery will be reduced to 0 Dth.
Joliet NGPL receipt will remain at 0 Dth.
Joliet Peoples receipt and delivery will be reduced to 0 Dth.
NNG Bluff Creek receipt will be available for the duration of the outage.

These capacity reductions begin Gas Day Tuesday, May 19, 2026, Timely Cycle and are anticipated to be in effect through Gas Day Saturday, May 23, 2026.

GPL does anticipate an impact to firm transportation services. Reservation rate credits will be applied pursuant to GPL's FERC Gas Tariff, General Terms and Conditions, Section 40.

Please contact your Commercial representative with any further questions.