| Capacity Constraint |
04/02/26 |
04/02/26 |
05/02/26 |
25987834 |
|
CAPACITY POSTING - TIM for April 03, 2026 through April 06, 2026 |
|
| Maintenance |
04/01/26 |
04/01/26 |
05/01/26 |
25988015 |
|
Holcomb Compressor Station Unit 2701 Maintenance (InvrnSEG), April 7-14, 2026 |
|
| Capacity Constraint |
04/01/26 |
04/01/26 |
05/01/26 |
25987824 |
|
CAPACITY POSTING - TIM for April 2, 2026 |
|
| Capacity Constraint |
03/31/26 |
03/31/26 |
04/30/26 |
25987819 |
|
CAPACITY POSTING - TIM for April 1, 2026 |
|
| Maintenance |
03/30/26 |
03/30/26 |
04/30/26 |
25988010 |
|
Construction and Maintenance Schedule Posting |
|
| Capacity Constraint |
03/30/26 |
03/30/26 |
04/30/26 |
25987815 |
|
CAPACITY POSTING - TIM for March 31, 2026 |
|
| Maintenance |
03/28/26 |
03/28/26 |
04/28/26 |
25988009 |
|
COMPLETED: West Lateral-100 Pigging (4246), ID2 Cycle, March 28, 2026 |
|
| Capacity Constraint |
03/27/26 |
03/27/26 |
04/27/26 |
25987814 |
|
REVISED: CAPACITY POSTING - TIM for March 28, 2026 through March 30, 2026 |
|
| Maintenance |
03/27/26 |
03/27/26 |
04/27/26 |
25987813 |
|
COMPLETED: Clementsville Compressor Station (ClemSEG) Eff. Eve Cycle for Gas Day March 28, 2026 |
|
| Maintenance |
03/27/26 |
03/27/26 |
04/27/26 |
25987812 |
|
COMPLETED: Corinth Compressor Station (CorinSEG) Eff. Eve Cycle for Gas Day March 28, 2026 |
|
| Capacity Constraint |
03/27/26 |
03/27/26 |
04/27/26 |
25987808 |
|
CAPACITY POSTING - TIM for March 28, 2026 through March 30, 2026 |
|
| Capacity Constraint |
03/26/26 |
03/26/26 |
04/26/26 |
25987412 |
|
CAPACITY POSTING - TIM for March 27, 2026 |
|
| Capacity Constraint |
03/25/26 |
03/25/26 |
04/25/26 |
25987117 |
|
CAPACITY POSTING - TIM for March 26, 2026 |
|
| Other |
03/24/26 |
03/24/26 |
04/24/26 |
25986518 |
|
Columbia Pipelines March 2026 Monthly Customer Update – Today, March 24, 1:30 PM CST |
|
| Capacity Constraint |
03/24/26 |
03/24/26 |
04/24/26 |
25986515 |
|
CAPACITY POSTING - TIM for March 25, 2026 |
|
| Capacity Constraint |
03/23/26 |
03/23/26 |
04/23/26 |
25987108 |
|
CAPACITY POSTING - TIM for March 24, 2026 |
|
| Maintenance |
03/20/26 |
03/20/26 |
04/20/26 |
25986511 |
|
West Lateral-100 Pigging (4246), March 27-30, 2026 |
|
| Capacity Constraint |
03/20/26 |
03/20/26 |
04/20/26 |
25986510 |
|
CAPACITY POSTING - TIM for March 21, 2026 through March 23, 2026 |
|
| Maintenance |
03/19/26 |
03/19/26 |
04/19/26 |
25986509 |
|
Construction and Maintenance Schedule Posting |
|
| Capacity Constraint |
03/19/26 |
03/19/26 |
04/19/26 |
25986508 |
|
CAPACITY POSTING - TIM for March 20, 2026 |
|
| Other |
03/18/26 |
03/18/26 |
04/18/26 |
25985653 |
|
Columbia Gulf Flexible Balancing PAL Open Season #2026-0318 |
|
| Capacity Constraint |
03/18/26 |
03/18/26 |
04/18/26 |
25985652 |
|
CAPACITY POSTING - TIM for March 19, 2026 |
|
| Force Majeure |
03/18/26 |
03/18/26 |
04/18/26 |
25985651 |
|
LIFTED: Force Majeure: Mainline-300 (AlexSEG) Effective ID1 Cycle for March 18, 2026 |
|
| Capacity Constraint |
03/17/26 |
03/17/26 |
04/17/26 |
25985650 |
|
CAPACITY POSTING - TIM for March 18, 2026 |
|
| Computer System Status |
03/16/26 |
03/16/26 |
04/16/26 |
25985638 |
|
TC eConnects Security Enhancement Notice |
|
| Capacity Constraint |
03/16/26 |
03/16/26 |
04/16/26 |
25985631 |
|
CAPACITY POSTING - TIM for March 17, 2026 |
|
| Maintenance |
03/13/26 |
03/13/26 |
04/13/26 |
25985630 |
|
UPDATE: Alexandria Compressor Station Unit 908 Maintenance (AlexSEG) March 20-25, 2026 |
|